The authorities shall decide in each individual case on the required water endowment and any other measures which may be necessary to protect waters below the point of withdrawal.
They may specify temporally variable required water endowments. Residual flows shall not fall below those specified in Articles 31 and 32.
The authorities shall consult the competent agencies before making their decision; in cases where the withdrawals in question concern hydropower plants with gross production in excess of 300 kW, they shall also consult the federal government.